Thursday 31 March 2011

Update 31/03/11

Lots of progress on the groundwork this week. We've been told that the new (moved) pedestrian gate will be complete by Monday (3rd April), making access to pick up and collect children easier.

The fire doors in the school hall should also be completed by Monday, which will mean another update to our emergency evacuation plan. Once these doors are in use, we will be practicing our Fire Drills once again, using the new routes.

The milestone date for the next BIG part of the build is May 16th, when the new build walls and floors arrive, pre-assembled and ready to install onto the concrete base. This process we expect to happen very quickly- the building should grow out of the ground before our eyes!